IVC ENDÜSTRİYEL VANA SAN. VE TİC. LTD. ŞTİ. BUSINESS CENTER BUILDING
Project Start Date: 01.06.2013
Project End Date: Ongoing
Total Construction Area: 1,345 sqm

The plaza in Istanbul, Ümraniye, Şerfiali district is located on a lot of 450 sqm and consists of 2 basements, a ground floor, 2 regular floors and a penthouse.

Beginning from the building license stage, all project design, basic structure, fine structure, electrical, mechanical application, infrastructure and landscape works will be carried out by our company.
BİRLEŞİM MÜHENDİSLİK MAIN OFFICE AND FACTORY BUILDING ( LEED GOLD )
Project Start Date: 01.04.2011
Project End Date: 01.04.2012
Total Construction Area: 7,491 sqm

It is located in Istanbul, Dudullu Organized Industrial Zone. Birleşim Mühendislik main office and plant have been positioned together.

The plant section of the building with 7,491 sqm area consists of production, storage and office areas, while the management section consists of meeting rooms, 100-person training and seminar hall, and mess hall.

Our project has been awarded with LEED GOLD certificate. Since the design stage, the building has been designed and constructed according to LEED criteria. For energy recovery and savings, special facade glasses, high efficiency condensing boilers, VRV cooling system, floor heating, heat recovery air handling units, and Dali ballast system for lighting automation and corresponding lighting fixtures have been used in the building.

Rainwater is collected from roof and surroundings, treated, and used in both landscape irrigation and in reservoirs. It is a comfortable and environmentally conscious building with high energy efficiency.
MEYER GROUP
Project Start Date: 01.04.2012
Project End Date: 01.05.2012

Project design and application of fine structure works of 4 regular floors and 2 basements of the 1,600 sqm plaza located in Istanbul, Ümraniye, Şerifali district.

Project design and application of painting, drywall, aluminum glass partitions, ceramic tiling, laminated parquet flooring, carpet flooring, wallpaper application, moving furniture, electrical and mechanical works have been completed.
BİRLEŞİM PLAZA 3
Project Start Date: 05.07.2010
Project End Date: 30.11.2010
Total Construction Area: 1,350 sqm

The plaza in Istanbul, Ümraniye, Şerfiali district is located on a lot of 540 sqm and consists of 2 basements, a ground floor, 2 regular floors and a penthouse.

Beginning from the building license stage, all project design, basic structure, fine structure, electrical, mechanical application, infrastructure and landscape works were performed by our company.
BODRUM VILLAS
Project Start Date: 10.01.2009
Project End Date: 30.06.2009
Total Construction Area: 760 sqm

The project consists of 4 luxury villas located on a lot of 1,100 sqm in Bodrum, Göltürkbükü district.

The villas have 3 floors ( basement, ground floor, and the first floor ), and each have a total usage area of 190 sqm.

Natural stone facing has been preferred to harmonize with Bodrum architecture.
ISIK PLAZA
Project Start Date: 02.05.2008
Project End Date: 15.10.2008
Total Construction Area: 700 sqm

The plaza in Istanbul, Ataşehir district is located on a lot of 280 sqm and consists of a basement, a ground floor, 2 regular floors and a penthouse.

Beginning from the building license stage, all project design services ( architectural, static, electrical, mechanical ), basic structure, fine structure, electrical, mechanical application, infrastructure and landscape works were performed by our company.
DANFOSS PLAZA
Project Start Date: 01.02.2008
Project End Date: 01.04.2008
Total Construction Area: 1,075 sqm

Project design and application of all fine structure works of 3 regular floors and 1 basement of the plaza located in Istanbul, Ümraniye, Şerifali district.

Project design and application of all painting, drywall, aluminum glass partitions, ceramic tiling, laminated parquet flooring, electrical and mechanical works have been completed.
SİLİVRİ PALMIA RESIDENCES
Project Start Date: 01.10.2006
Project End Date: 01.08.2008
Total Construction Area: 11,600 sqm

The Palmia Residences in Istanbul, Silivri district is located on a lot of 8,500 sqm and consists of 4 blocks and 60 flats.

In the project, there are 48 regular flats sized between 150 and 170 sqm, and 12 penthouse duplex lofts sized between 210 and 230 sqm.

Each flat has been assigned one car parking space in the parking garage of total 2,500 sqm.

There is a 90 ton capacity water tank to meet the water requirement of the site and a full generator that also backs up interiors of the flats against power cuts.

In the facilities, for which a 3 dunam area has been reserved in the project, there are basketball and mini football fields, a decorative pool, a wooden playground, and a gazebo.

There is 24 hour security cam surveillance in the site.
BIRLESIM PLAZA SERIFALI
Project Start Date: 01.02.2005
Project End Date: 01.05.2006
Total Construction Area: 4,200 sqm

The plaza in Istanbul, Ümraniye, Şerifali district is located on 1,800 sqm area and consists of 2 blocks, each with 2,100 sqm usage areas.

There are 2 basements, one ground floor, 4 regular floors, and a penthouse in each block.
KURTKOY GOKKUSAGI VILLAS
Project Start Date: 01.11.2002
Project End Date: 01.03.2005
Total Construction Area: 8,750 sqm

They consist of 25 villas built on 10,162 sqm area in Istanbul, Kurtköy district.

3,000 sqm of 10,162 sqm land has been reserved as for recreational facilities and include a swimming pool, playground, basketball and mini football fields. .

Each villa has 4 floors and total 350 sqm usage area.